Reagrio is developing the project as Build, Own, Operate (BOO). Reagrio will Own and Operate the facility and the RFP issued is aimed to contract the Build part until Final Completion.
For the Build part, the Bidder shall design, refurbish/construct, install & commission the solution. This is Milestone Substantial Completion. After Substantial Completion, the Bidder shall correct any non-conformities of the facility, secure stable processes and that the output requirements are proven and met. This is Milestone Final Completion (=Commercial Operations Date).
When Final Completion is reached, the facility incl operation & maintenance responsibility will be transferred to Reagrio’s SPV during Handover. Reagrio’s SPV may assume Operations & Maintenance (O&M) responsibility or outsource it. This O&M outsourcing will be a separate agreement.
Reagrio’s SPV will hire the required staff and make them available to the Bidder for training and competence development.
Maintenance agreements with selected equipment providers shall be signed and are within the scope of this RFP. These maintenance agreements will be transferred to Reagrio’s SPV during the Handover.
The SPV may take on the responsibility of O&M or outsource this service element to an external O&M company.